Assembly of a dedusting system

Firstly the assembly of the steel frame support
Then the pre-assembly of all attachments is done on the ground, as far as possible.
The pre-assembled upper part is mounted on the central part
The upper- and middle part are mounted on the filter cone.
The entire plant is lifted and bolted to the steel frame structure.
Then the ladder is mounted
After the filter unit is positioned fan and chimney can be placed.
Finally, the assembly of the filter bags and support buckets etc will be done.